No 1 and 3 Reactors over temp
Posted by JAC on 3/23/2011, 6:22 am
http://english.kyodonews.jp/news/2011/03/80489.html


TOKYO, March 23, Kyodo

Work to restore power and key cooling functions was disrupted again Wednesday at the crisis-hit Fukushima Daiichi nuclear plant after smoke caused workers to evacuate, while fear of radioactive pollution spread to Tokyo with an alert not to give tap water to infants.

The plant operator Tokyo Electric Power Co. said it learned at around 4:20 p.m. that black smoke was seen rising at the No. 3 reactor building, leading to evacuation of workers from the four troubled reactors, but added about an hour later that it was receding.

The radiation level was unchanged shortly afterward, meaning the smoke caused no massive release of radioactive materials, the government's nuclear safety agency said. Smoke was also seen billowing from the No. 3 building on Monday.

It also turned out that the surface temperatures of the No. 1 and No. 3 reactor vessels have topped the maximum levels set by their designers, now that they can be measured due to battery-based backup power, the Nuclear and Industrial Safety Agency said.

In Tokyo, the metropolitan government said radioactive iodine exceeding the limit for infants' intake was detected in water at a purification plant, apparently due to the ongoing crisis at the power station crippled by the March 11 massive quake and tsunami.

At the plant run by the utility known as TEPCO, all six reactors were reconnected to external power as of Tuesday night and workers scrambled to check each piece of equipment, such as data measuring instruments and feed-water pumps, before transmitting power to them.

With the work, TEPCO aimed to first restore a pump by Thursday to inject fresh water into the core of the No. 3 reactor, instead of seawater that has currently been poured using fire pumps, the nuclear agency said.

While the maximum vessel temperature set by the reactors' designers is 302 C degrees, the surface temperature of the No. 1 reactor vessel briefly topped 400 C degrees and dropped to about 350 C degrees by noon, and that of the No. 3 reactor vessel stood at about 305 C degrees, the agency said.

Although the facilities are not expected to start melting at those temperatures, according to agency spokesman Hidehiko Nishiyama, TEPCO increased the amount of seawater injected into the No. 1 reactor by nine times to help cool it down.

Nishiyama said TEPCO will continue to inject massive amounts of water into the No. 1 reactor so as not to raise the pressure in the reactor. High pressure in the reactor increases the risk of damage to the facility, and workers would be required to release radioactive steam from the reactor to lower the pressure.

At the No. 2 reactor, workers have been unable to replace some parts to help revive its internal cooling systems since Friday as high-level radiation amounting to at least 500 millisieverts per hour was detected at its turbine building, the spokesman also said.

Water-spraying operations, meanwhile, continued in the morning at the No. 4 reactor unit to help cool down its spent nuclear fuel pools, using trucks with a concrete squeeze pump and a 50-meter arm capable of pouring water from a higher point.

But similar operations for the No. 3 reactor were put off.

TEPCO also said two workers who had been installing a makeshift power source from Tuesday night were injured and taken to hospital, but they were not exposed to radiation.

Lighting in the No. 3 reactor's control room was restored Tuesday night, a key step toward regaining control of the situation as operators have been unable remain in any control rooms for long hours due to high radiation levels and power outages.

After the March 11 earthquake and massive tsunami knocked out power at the plant, the cooling functions failed at the No. 1, No. 2 and No. 3 reactors, while the pools storing spent nuclear fuel at the No. 1, No. 2, No. 3 and No. 4 units have also lost all their cooling functions.

In addition to efforts to douse the pools with water sprayed from outside, workers are also attempting to inject water by reviving internal cooling systems, according to the nuclear agency.

As part of routine monitoring activities, helicopters of the Self-Defense Forces examined temperatures at the Fukushima nuclear power station Wednesday morning.

==Kyodo