TEPCO has been authorized to begin injection of N2 into primary containment vessel of Unit 1
Posted by JAC on 4/6/2011, 9:08 pm
http://www.iaea.org/newscenter/news/tsunamiupdate01.html

Fukushima Nuclear Accident Update (6 April 2011, 15:15 UTC)

Japanese authorities have informed the IAEA that TEPCO has been authorized to begin injection of nitrogen into the primary containment vessel (PCV) of Unit 1 at the Fukushima Daiichi nuclear power plant.

Injection of nitrogen is intended to displace oxygen inside the containment vessel, thereby reducing a risk of explosion due to the combustible combination of hydrogen and oxygen.

33
In this thread:
Radioactive leak plugged at Japan nuclear plant - ArgosyTn, 4/6/2011, 1:20 pm
  • TEPCO has been authorized to begin injection of N2 into primary containment vessel of Unit 1 - JAC, 4/6/2011, 9:08 pm
  • NRC thinks No 2 going China - JAC, 4/6/2011, 8:59 pm
< Return to the front page of the: message board | monthly archive this page is in